Return to DOE Report Table of Contents

Return to Preliminary Design Services, Coal Conversion Demonstration Plants Table of Contents

Project POGO: Coal Refinery Complex Conceptual Design / Economic Analysis; Power, Oil, Gas, Other Products.
R & D Report No. 114, Interim Report No. 6 - 1977

O'Hara, J. B.
Jentz N. E.
Syverson, H. T.
Hervey, G. H.
Teeple, R. V.
Bela, A.
Klumpe, H. W.
Loran, B. I.
Mills, E. A.
Newton, R. J.
 

The Ralph M. Parsons Company

Table of Contents (513kb)

1

Introduction (153kb) 1-1
2 Summary (259kb) 2-1
3 Design Parameters (336kb) 3-1
4 Summary Facility Description (141kb) 4-1
5 Unit Description (2.36MB) 5-1
6 Process Flow Diagrams (4.3MB) 6-1
7 Products: Marketability and Characteristics (113kb) 7-1
8 Material Balance (37.8kb) 8-1
9 Energy Balance (104kb) 9-1
10 Utilities (119kb) 10-1
11 Environmental Factors (769kb) 11-1
12 Startup Procedures (158kb) 12-1
13 Major Equipment Summaries (3.35MB) 13-1
14 Economics (1.94MB) 14-1
15 Design Data Base (439kb) 15-1
16 Projected Performance (661kb) 16-1
17 Potential Improvements (233kb) 17-1
18 Alternate 1: Southern Appalachian Region of the Eastern Coal Province (672kb) 18-1
19 Alternate 2: Powder River Region of the Rocky Mountain Coal Province (908kb) 19-1
20 Literature Cited (170kb) 20-1
 

Appendices (692kb)

A Excerpts from "Project Pogo, Cog Refinery Design Criteria Report" A-1
B Site Conditions B-1