Reel 191
Page Bldg.
1-2 18 List of equipment – tar chamber
3 18 Ground plan – Tar chambers 1 & 2
4 18 Flow diagram. Tar chambers.
5 Piping diagram
6 19 List of equipment – Benzine chamber
7 19 Plan layout
8 19 Flow diagram
9 20 Intermediate storage tank. List of equipment
10 21 Pump house – list of equipment
11 22 Intermediate storage tank No. 2, List of equipment.
12 Flow diagram of gas scrubbers.
13-17 23 Distillation plant. List of equipment.
18 23 High pressure stabilizer.
19 23 Low pressure stabilizer (Plant B.)
20 23 Flow diagram of refining plant “A”
21 23 Flow diagram of refining plant “B2”
22 23 Flow diagram of refining plant “C”
23-24 25 Fuel gas plant. List of equipment.
25 Flow diagram of Linde propane-butane plant.
26 28 Benzine scrubber – List of equipment.
27 28 Benzin scrubber – Plan layout.
28 28 Benzin scrubber – Flow diagram.
29 30&55 Piping diagram of service water
30 29 List of equipment. Water cooler.
30 30 List of equipment. Pump house.
30 31 Storage tank for Benzin. List of equipment.
31 32 Mixed-gas plant and pump house – List of equipment.
32 33 Fuel gas storage. List of equipment.
32 36 Nitrogen gas holder.
32 38 Gas Holder.
32 39 Waste products for railroads.
33 40 Storehouse
33 41-44 Transfomers
33 45 Gas holder
33 46 Winkler water purification plant.
33 47-48 Switch-gear.
33 49 “Waschkau”
33 50 Loading of freight cars.
34 51 Blower for alkazid process.
34 52 Sulfur storage
34 53 Garage
34 54 “Pfortnerhaus”
34 55 Water pumps and storage tanks.
35 51 Flow diagram of blowers.
36 56 Settling tank.
36 57 Settling tank.
36 58 Air raid shelter.
36 59 Scales.
36 60 Controls for steam pressure regulation.
36 61-64 Storage for foaming agents.
36 65 Storage for miscellaneous materials.
37 Flow diagram gasometer.
38 Compressed air piping diagram.
39 Piping diagram of drinking water.
40 Piping diagram of gas lines.
41 Piping diagram of phenol & waste water
42 Piping diagram of hydrogenation gas.
43 Piping diagram of steam lines.
44 Piping diagram of water lines.
45 Wiring diagram.
46 Wiring diagram for 6000-volt lines.
47 Wiring design for 500-volt lines.
48 Wiring design for 220-volt lines for lighting.
Page Bldg.
1 Flow diagram.
2-4 1 Oxygen production plant. List of equipment.
5 1 Plan layout
6 1 Flow diagram.
7 2 Oxygen receiver
7-9 3 Water gas production – List of equipment.
10 3 Plan layout.
11 3-4 List of equipment
12 5 List of equipment. Blowers.
13 5 Plan layout.
14 6 List of equipment. Purification towers.
15 6 Plan layout.
16-17 7 Contact plant. List of equipment.
18 7 Plan layout.
19 9 Compressors – List of equipment.
20 11 Vacuum plant. List of equipment.
21-23 9 CO2 Purification. List of equipment.
24-25 9 CO Purification. List of equipment.
26 9 Layout plan.
27 9 Flow diagram – CO2 scrubbers.
28 10 CO2 gas holder.
29 11 Pump house. List of equipment.
30 11 Vacuum pump. List of equipment.
31-32 11 Contact plant. List of equipment.
33 11 Layout plan.
34 11 Flow diagram of liquor & pressure lines.
35 11 Flow diagram of contact plant.
36 11a Flow diagram of vacuum plant.
37 Flow diagram of pump.
38-39 12 Alkazid plant. List of equipment.
40 12 Alkazid plant. Layout plan.
41 12 Alkazid plant – Flow diagram.
44 13-14 List of equipment.
45-48 15 Dephenolization plant. List of equipment.
49 15 Plan layout.
50 15 Flow diagram of phenol distillation.
51 15 Flow diagram of dephenolization.
52-53 16 Tar separator. List of equipment.
54 16 Tar separator. Layout plan.
55 16 Tar separator. Flow diagram.
Page Bldg.
1 1 Oxygen plant – Flow diagram.
2-7 1 Oxygen plant. List of equipment.
8 3/57 Water gas plant. Layout plant.
9-20 Winkler water gas plant – List of equipment.
21 6 Disulfurization plant. Plant layout.
22 7 Pump house. Layout plan.
23 7 Hydrogenation plant. Layout plant.
24 7 Hydrogenation plant. Section B-B; and C-C
25-29 7 Hydrogenation plant. List of equipment.
30 9 Gas compressors.
31 9 Gas compressors – Basement.
32 9 Gas compressors – Section A-B.
33-38 9 List of equipment.
39 11 Injector pumps. Layout plan.
40-45 11 List of equipment.
46 11 Injector pumps. Layout plan.
47-49 11 List of equipment.
50 14 Hydrogen sulfide gas holder.
51-55 16 Tar separator; treatment of foul oil, etc. List of equipment.
56 17 Tar storage tank – Layout plan.
57-58 17 List of equipment.
59 18 T.T.H. Chamber. Layout plan.
60 18/19 Oven chamber. Layout plan.
61-63 18/19 List of equipment.
64 19 Gas-phase chamber. Layout plan.
65-66 19 Gas-phase chamber. List of equipment.
67-69 21 Pump house & misc. List of equipment.
70 23 Distillation plant. Plan layout.
71-72 23 Distillation plant. List of equipment.
73 26 Gas-phase hydrogenation rich-gas holder. List of equipment.
74 27 Lean-gas holder. List of equipment.
75-76 30 Pump house. List of equipment.
Page Bldg.
1-3 31/32 Benzin storage tank. List of equipment.
4 33/35 Diesel oil storage tank. List of equipment.
5 36 Work room. Plant layout of ground floor.
6 38 Nitrogen gas holder. List of equipment.
7 40 Store room.
8-10 48 CO and CO2 plant. Plan layout.
11-18 48 CO and CO2 plant. List of equipment.
19 54 Water filter plant. Layout plan.
20 54 Water plant – pump house. Layout plan.
21 54 Water plant – pure water receiver. Layout plan.
22 55 Settling tank. Layout plan.
23-30 54/55 List of equipment.
31 57 Bunkers, screening, & pulverizing plant.
32-35 57 List of equipment.
36-38 58 Water purification plant.
39-43 65 Waste water treatment. List of equipment.
44 67 Water purification plant.
45 70 Water works. Layout plan.
46 90 Power station.
47-71 89/90 Power station. List of equipment and products used, analyses of
fuel.
55 Koppers Handbook of Fuel Technology. Copyright 1937 by Heinrich Koppers G.m.b.H. Cover page.
1. Capacity of production of Buna Werk Schkopau plant:
a. Before the first air raid;
b. Estimated capacity of plant in its present condition;
c. Estimated capacity of plant without supply of electric current from outside.
2. Products and quantities which are required per month in case (c) and naming also the factories and places where they were manufactured so far.
3. List of stacks of raw materials on hand with details on how long they will last in case (c).
4. Stacks of finished products on hand.
57 Processes used at Buna-Werk Schkopau. About 100 pages. Dates range from 1937 to 1939. A rough draft probably used by some of the superintendents of the German plant at Schkopau as a ready reference in connection with plant operation. It is separated into seven portions, as follows:
2. Calcium Carbide manufacture
3. Chlorine and Sodium Hydroxide
4. Ethylene oxide and related side reaction materials
5. Preparation of phthalic anhydride
6.
Preparation of Styrene
Preparation of Aldol
7. Preparation of vinyl chloride