Overall Project Objectives |
1 |
Summary of all Previous Work Performed on the
Contract |
3 |
Work Performed |
3 |
Major Technical Problems Encountered |
3 |
Major Accomplishments |
3 |
Conclusions and Significant Findings |
4 |
Specific Objectives for the Current year |
7 |
Work Plan for the Current Year |
9 |
Task VII. Technical Services |
9 |
Task IX. Obtain Design Data |
9 |
Task X. Design, Construct, and Operate and Adiabatic
Reactor System |
9 |
Task XI. Obtain adiabatic Design data for Evaluation
of Raw-Gas Process Schemes |
9 |
Work actually performed during the current year |
11 |
Obtaining Design Data for the Direct Methanation
Process Using a Slaging Lurgi Gasification - type raw gas |
11 |
Evaluation of GRI-C-525 Catalyst for
High-Temperature Resistance |
12 |
Obtaining Design Data for the Direct Methanation
Process using a Westinghouse Gasification -Type Raw Gas |
12 |
Catalyst Life |
12 |
Evaluation of a GRI-C-V catalyst |
12 |
Major Achievements during the Current year |
15 |
Major Technical Problems Encountered during the year |
17 |
Conclusions |
19 |
Specific objectives and work plan for the next year |
21 |
Task XII. Test Direct Methanation Catalysts |
21 |
Task XIII. Determine Catalyst Life |
21 |