Return to DOE Reports Table of Contents - S

Pinon Pine Power Project.  Annual Report.  August 1992 – 1993.

Sierra Pacific Power Company

In this pdf format, this document has 72 pages and is 3.40 MB.

Table of Contents

1.

Executive Summary

6

2.

Introduction and Background

7

2.1

IGCC Technology Overview

7

2.2

IGCC Development History

9

2.3

Project Selection and Cooperative Agreement

10

2.4

Description of Existing Tracy Station

10

3.

Project Objectives

16

3.1

Overview of Objectives

16

3.2

Description of Project Phases

16

3.3

Accomplishments

17

4.

Plant Description

21

4.1

Pinon Pine Power Project

21

4.2

Gasifier Island

24

4.3

Combined-Cycle

26

4.4

Offsites

27

5.

Scope of Work

32

5.1

General Project Requirements

32

5.2

Project Management

33

5.3

Engineering and Design

34

5.4

Procurement

38

5.5

Construction

39

5.6

Environmental Permitting and Licensing

41

5.7

Operation

44

6.

Technical Impacts on Schedule

45

7.

Conclusions and Look Ahead

46

8.

Appendices

46

1.

Location of Pinon Pine IGCC Power Project

47

2.

Pinon Pine IGCC Power Project Schematic

48

3.

Process Flow Diagrams

49

4.

Summary Bar Chart Project Schedule

67

5.

Photographs pf existing Tracy Facility

68