Note from the editors only selected documents from this microfilm reel have been completely processed and presented below in cleaned and grouped format (bag 2168 items 1 through 2b21, identified by HTML links). The remainder of the reel is not related to the Fischer-Tropsch process, and therefore complete processing cannot be justified at this time.
We are, however, making the entire reel contents available in raw image format, although in a small number of relatively large files (rather than a very large number of small individual images). Anyone interested in pursuing the non-FT related material on this reel may find the document in these larger raw files.
Images 0001-0200 File size ca. 20 Mb
Images 0201-0400 File size ca. 15 Mb
Images 0401-0600 File size ca. 29 Mb
Images 0601-0746 File size ca. 17 Mb
Bag 2168(4.03) I.G. Ludwigshafen Oppau
Item
1. Continuation of Section 13, from T.O.M. Reel 2, Synthesis Gas Production. 2 pages.
2. Monthly reports on Fischer synthesis Plant at Wintershall A. G. Lutzkendorf consists of summary sheet under the following headings: 1, coal used; 2. heating gas; 3, synthesis gas; 4, gas purification; 5, Fischer synthesis and 6, oxygen and nitrogen. The Summary Sheet is followed by Detail sheets of explanatory notes.
The following individual items obtain:-:-
2b. (1) Monthly report Group A, August, 1943, Summary Sheet, 1 page. Detail Sheet, 1 page.
(3) Monthly Report Group A, June, 1943. Summary Sheet, 1 page. Detail Sheet, 1 page.
(5) Monthly Report Group A, September, 1943. Summary Sheet, 1 page.
(6) Monthly Report D, May, 1944. Utilities Requirements Summary Sheet, 2 pages.
(7) List of Personnel Chemists and Engineers, gives vital statistics. Some pages illegible. 46 pages.
(8) List of personnel at Oberrheim. 56 pages. Variable quality. Some excellent, some illegible.
(10) A letter on time needed to give a lecture on the item in #9. 1 page.
(15) Monthly Report Group A. Summary Sheet on Fischer Synthesis. 4 pages
(16) Monthly Report Group B. February, 1944. Summary and Detail Sheets. 2 Pages.
(17) Monthly Report Group C. February, 1944. Summary and Detail Sheets. 2 pages.
(18) Monthly Report Group D. October, 1943. Utilities Requirements. 2 pages
(19) Monthly Report. September, 1943. Utilities Requirements. 2 pages. Summary Sheet on Progress. 4 pages
(20) Monthly Report Group C. September, 1943. 4 pages.
(21) Monthly Report Group B. August, 1943. 2 pages.
(22) An Experiment by F. Winkler, dated July 26, 1939. Ethylene (from the hydrogenation in the electric arc) enriched by copper wash. 5 pages.
(23) Paper on The Continous Production of Succinic Acid from Tetra-hydro-furane and nitric acid. October 6, 1942.
19 pages
(24) Procedure for the production of n and I butyraldehyde or the corresponding alcohols A write-up for a patent.
March 19, 1943. 4 pages.
(25) Procedure for the production of Poly-hydric alcohols. A patent application (copy). March 6, 1943. 1 page.
(26) Procedure for the production of dichlorethane. A patent application November 23, 1943. 2 pages.
(27) Procedure for the production of ethylene glycol. Patent application July 9, 1942. 7 pages
(28) Procedure for the production of Halogin Acid Solutions. Addition to Patent Application #1.71 303 IV b 12i.
March 26, 1942. 4 pages.
(29) Steam and Electricity (Economy of) Requirements at Lutzendorf. 14 pages.
(30) Letter Dated November 25, 1940 to the Ministry of Economics Division of Power on Power requirements. 2
pages.
(31) Report on Power Production and Operation Safety. 2 pages
(32) Directive on Work Schedule. 1 page.
End of Bag #2168 Target No. 30/4.03
1. Bag #2745 Target 30/4.08 Gelsenberg
(Noto This new target number continues on the same roll)
2. (1) Summary Sheet of Bag 2745 Target 30/4.08 lists 20 items (18 of which are on this roll which is identified as
Roll 3). The Summary sheet is in English.
(2) Title page in English Coal Hydrogenation. 1 page.
(3) Item #1 Monthly Report
(1) Operating Data on Hydrogenation works at Nordstern. 2 pages.
(2) Monthly Report March 1944. 2 pages.
(3) Monthly Report February 1944. 2 pages.
(4) Monthly Report Januray 1944. 2 pages
(5) Monthly Report December 1943. 2 pages
(6) Monthly Report October 1943. 2 pages
(7) Monthly Report September 1943. 3 pages
(8) Monthly Report August 1943. 3 pages
(9) Monthly Report July 1943. 2 pages
(10) Monthly Report June 1943. 2 pages
(11) Monthly Report May 1943. 2 pages
(12) Monthly Report March 1943. 2 pages
(4) Item #2 Monthly Total Balance Coal, Catakysts, Oil. In Engish. 1 page
(1) Total Balance Sheets October 1941 Januray 1940. 10 pages
(5) Item #3 Monthly Total Gas Balance December 1940 January 1940. 12 pages
(6) Item #4 Monthly Gas Summaries September 1941-January 1940. 16 pages
(7) Item #5 Monthly Total Shipments October 1941 January 1941. 10 pages
(8) Item #6 Monthly Barge Shipments. 8 pages
(9) Item #7 Monthly Summaries Shipping and Isobutane Plant September 1941 September 1940. 8 pages
(10) Item #8 Monthly Summaries A Middle Oil Distallation July 1941 December 1940. 14 pages
(11) Item #9 Monthly Summaries Distillation and Stabilizing, October 1941 January 1941. 11 pages
(12) Item #10 Monthly Summaries Centrifuge Plant October 1941 January 1940. 24 pages
(13) Item #11 Monthly Summaries Carbonization Plant, October 1941 January 1940. 24 pages
(14) Item #12 Monthly Summaries Coal Grinding, October 1941 January 1941 . 10 pages
(15) Item #13 Monthly Summaries Light Ends Recovery, July 1941. 23 pages
(16) Item #14 Monthly Summary Coal Stalls December 1940 December 1941. 22 pages
(17) Item #15 Monthly Summaries. Saturation and Splitting. October 1941 December 1940. 22 pages
(18) Item #16 Yearly Stall Operations Curves
1942 1943 (1) Monthly usage of stalls (chambers)
1942 1943 (2) Charges and yields
1942 1943 (3) Chemical operation data on coal phase-yields of different fraction.
Curves are ploteed with time as abscissa and % yields as ordinate.
(19) Item #17 Coal Stalls Effect of ash hydrogen loss-light hydrocarbons.
(1) Influences of ash content on coal phase hydrogen. 1 page
(2) Hydrogen losses and gaseous hydrocarbons in coal phase. 4 pages
(3) A short visit to Scholven Discussion the charging capicity of ovens with coal paste. 2 pages.
(20) Item # 18 Operation Reports Saturation and Splitting stalls
(1) June 1944 February 1944 plus general report. 8 pages
(2) Discontinuation and enlargement of operating stall operational period December 1940 March 1940 - gives reasons for discontinuation. 4 pages
(3) Pressure Drop Data through Equipment. 1 page.
(4) Machine Shop Forms. 3 pages
(5) Equipment List (use not stated). 1 page
(6) Discontinuation of Benzine Stall 305 (due to air raid) October 15, 1940. Rebuilt according to stall 301. 1 page
(7) Operation Report Benzine Stall 301. July 1944. 9 pages
(8) Report on remodeling of experimental stall 302 after 9th oeriod of operation. February 1943. 1 page
(9) Machine Shop Forms. 5 pages
(10) Equipment for experimental hydrogenation stall 302 3 compartments in chamber
February 20, 1943. 1 page
(11) Preliminary report on experimental stall 302. February 1943. 2 pages
(12) Discontinuation of Stall 302. April 21, 1941. 2 pages
(13) Report on operation of stall 302 covering different periods (6 in all). 27 pages
(14) Discontinuation of chamber 303. March 30, 1940. 4 pages
(15) Repair of chamber 303. 1 page
(16) memorandum air raid chamber 303. August 12, 1943. 1 page
(17) Flow sheet (gas-phase) Chamber 303. 1 page
(18) Memorandum foundation to Benzine chamber 303. August 1942. 1 page
(19) Production results with new hydrogenation catalyst at Politz. 1 page
(20) Experiences with catalyst 7846 W. 250 (composition not stated). 4 pages
(21) Installation of chamber 303 with catalyst 7846 W. 250. October 26, 1942. 3 pages
(22) Experiences with catalyst 7846 W. 250 with large scale operation 3 pages
(23) Preliminary Hydrogenation experiment with Catalyst 7846 W. 250 May 1942. 2 pages
(24) Visit of Dr. Schick from Leuna concerning injection of cold coal paste March 1942. 1 page.
(25) Operation report experimental chamber 303. August 1944. 7 pages
(26) Short report on last operational period experimental chamber 304 August 1944. 2 pages
(27) Preliminary testing of experimental chamber 304 building #22 December 1943. 3 pages
(28) Experimental chamber 304 April 1942. 6 pages
(28) Repair work and remodeling of chamber 304. March 1942. 1 page
(29) Repair work and remodeling of chamber 304. March 1942. 1 page
(30) Discontinuation of experimental chamber 304. June 1941. 1 page
(31) Operation report chamber 304. February 1943. 3 pages
(32) Operation report chamber 304. 1943. 4 pages
(33) Operational report chamber 304. 5 pages
(34) Method of measurement (preliminary testing) of chamber 304. 2 pages
(35) Repair work on chamber 305 after resumption of work in gas phase October 1942. 2 pages
(36) Construction of Oven 6434 of chamber 305. December 1941. 3 pages
(37) Discontinuation of Benzine chamber 305. October 7, 1941. 2 pages
(38) Discontinuation of Benzine chamber 304. October 15, 1940. 1 page
(39) Operation report chamber 305. July 20, 1940. 4 pages
(40) Operation report chamber 305. July 24, 1944. 4 pages
(41) Operation report chamber 305. July 24, 1944. 4 pages
(42) Operation report chamber 305. July 17, 1944. 3 pages
(43) Operation report chamber 305. July 26, 1944. 2 pages
(44) Operation report chamber 305. July 29, 1944. 4 pages
(45) Operation report chamber 305. August 23, 1944. 4 pages
(46) Reconstruction report of experimental chamber 306. September 2, 1943. 2 pages
(47) File notice #6641 on Benzine chamber 306. Sketch of chamber given. 4 pages
(48) Discontinuation of chamber 306 and enlargement to 3 compartments December 10, 1942
Sketch of chamber 306. 3 pages
(49) File notice February 17, 1942 on operation data. 1 page
(50) Removal of experimental chamber 306. February 1942. 5 pages
(51) Discontinuation of experimental chamber 306. January 10, 1942. 3 pages
(52) File notice operation on 306. 1 page
(53) Operation data on 306 covering different periods. 17 pages
(54) Preliminary testing of chamber 307. May 1944. 1 page
(55) Resumption of work on chamber 307. November 1943. 2 pages
(56) Repair of Raffinate oven in chamber 307. December 1942. 2 pages
(57) The Raffination of coal benzine. Curve of production % vs. month. Flow diagram of chamber 307. 5 pages
(58) File notice. February 1942 Operation Data. 1 page
(59) Operation report chamber 307 covering various periods. 10 pages
(60) List of charges in various chambers. 1 page.
(61) Discontinuation of gas phase August 1942. 5 pages
(62) Pressure release and washing of gas container. October 1942. 1 page
(63) Scheme for releasing the pressure in gas phase. October 1942. 2 pages
(64) Discontinuation of Gas Phase. October 1942. 3 pages
(65) Repairs on Gas Phase Equipment during Plant Discontinuation September 1942. 2 pages
End of Roll #3.