Table of Contents

I List of Figures 5
II Executive Summary 6
III Results, Discussion and Preliminary Conclusions 7
IV List of Major Activities Accomplished in 4Q2000 8
V List of Major Activities for 1Q2001 9
VII Graphs
  A Phase I, Planned Expenditures vs. Actual Expenditures 11
B Phase I, Planned DOE Expenditures vs. Actual DOE Expenditures 12
C Phase I, Planned vs. Actual Progress 13
VIII Schedule - MS Project schedule updated through December 31, 2000 15