Table of Contents
Introduction |
1 |
Background Information |
2 |
|
Project Inception and Objectives |
2 |
Plant Description |
9 |
Project Management |
15 |
Major Activities and Milestones |
17 |
Activities through December 1993 |
24 |
|
Phase I Activities |
24 |
Phase II Activities |
28 |
Phase III Activities |
28 |
Budget Period 1 Activities |
28 |
Budget Period 2 Activities |
29 |
1994 Activities and Milestones |
31 |
Appendix A – Glossary of Acronyms |
Appendix B – List of Figures |
Appendix C – List of Technical and Trade Publications Concerning the WRCGRIP |
|