Executive Summary |
5 |
I |
Introduction |
10 |
II |
Project/Process Description |
11 |
|
II.A |
Project Description |
11 |
II.B |
Need for the Technology Demonstration |
14 |
II.C |
Promise of the Technology |
14 |
II.D |
Technology Description |
14 |
|
II.D.1 |
Coal Handling |
14 |
II.D.2 |
Air-Separation Unit |
15 |
II.D.3 |
E-Gas™ Gasifier |
15 |
II.D.4 |
Syngas Conditioning/Cleanup |
17 |
II.D.5 |
Power Block |
20 |
II.E |
Project Implementation |
20 |
II.F |
Project Objective and Statement of Work |
21 |
III |
Technical and Environmental Review |
24 |
|
III.A |
Technical Results |
24 |
|
III.A.1 |
Air-Separation Unit |
25 |
III.A.2 |
Coal Handling |
26 |
III.A.3 |
Gasification |
27 |
III.A.4 |
Syngas Cooling and Particulate Removal |
27 |
III.A.5 |
Chloride Scrubbing System and COS Hydrolysis |
28 |
III.A.6 |
Low-Temperature Heat Recovery and Syngas Humidification |
28 |
III.A.7 |
Acid-Gas Removal, Sulfur Recovery, and Sour-Water Stripping |
29 |
III.A.8 |
Power Block |
29 |
III.A.9 |
Operations Feeding Petroleum Coke |
29 |
III.B |
Environmental Performance |
33 |
IV |
Market Analysis |
35 |
|
IV.A |
Market Size/Commercialization |
35 |
IV.B |
Economics |
37 |
|
IV.B.1 |
Capital Costs |
37 |
IV.B.2 |
Operating Costs |
37 |
IV.B.3 |
Cost of Electricity |
37 |
V |
Conclusions |
39 |