COOPERATIVE AGREEMENT |
i |
DISCLAIMER |
ii |
ABSTRACT |
iii |
TABLE OF CONTENTS |
iv |
LIST OF TABLES |
vi |
LIST OF FIGURES |
vii |
1.0 |
EXECUTIVE SUMMARY |
1 |
|
1.1 |
INTRODUCTION |
1 |
1.2 |
PLANT DESIGN |
1 |
1.3 |
EXPERIMENTAL |
1 |
1.4 |
RESULTS AND DISCUSSION |
2 |
1.5 |
CONCLUSIONS |
2 |
2.0 |
INTRODUCTION |
1 |
|
2.1 |
BACKGROUND |
1 |
2.2 |
PROJECT OUTLINE AND OBJECTIVES |
1 |
2.3 |
PROJECT PARTICIPANTS |
2 |
3.0 |
PLANT DESIGN STUDY & ECONOMIC ANALYSIS |
3 |
|
3.1 |
STUDY BASIS |
3 |
|
3.1.1 |
Plant Design Basis |
3 |
3.1.2 |
Site Characteristics |
3 |
3.1.3 |
Biomass Fuel Charactertistics |
3 |
3.1.4 |
Emissions Standards |
4 |
3.2 |
PLANT DESCRIPTION |
5 |
|
3.2.1 |
Overall Plant Description |
5 |
3.2.2 |
Systems and Components of the Plant |
6 |
3.2.3 |
Implementation Steps |
7 |
3.3 |
MAJOR PLANT AREAS |
15 |
|
3.3.1 |
Biomass Drying System |
15 |
3.3.2 |
Gasification Plant |
17 |
3.3.3 |
Boiler Modification and Internal Air Heating |
31 |
3.3.4 |
External High Temperature High Pressure Air Heater
AH-1 |
46 |
3.3.5 |
Power Generation |
47 |
3.3.6 |
Heat Recovery |
54 |
3.3.7 |
Balance of Plant |
55 |
3.3.8 |
Construction Schedule |
64 |
3.4 |
PLANT OPERATION |
65 |
3.5 |
PLANT PERFORMANCE |
70 |
|
3.5.1 |
Feed/Product Summary |
70 |
3.5.2 |
Efficiencies |
71 |
3.5.3 |
Emissions Inventory |
71 |
3.6 |
PLANT LAYOUT |
73 |
3.7 |
PLANT PERMITTING REQUIREMENTS |
74 |
3.8 |
CAPITAL COST ESTIMATE |
78 |
|
3.8.1 |
Cost Estimating Approach and Basis |
78 |
3.8.2 |
Data Source for the Estimate |
79 |
3.8.3 |
Estimated Capitol Cost |
80 |
3.9 |
OPERATING AND MAINTENANCE COST ESTIMATE |
80 |
3.10 |
ECONOMIC ANALYSIS |
83 |
|
3.10.1 |
Annual Savings |
83 |
3.10.2 |
Annual Expenses |
84 |
3.10.3 |
Payback Period |
84 |
3.10.4 |
Demonstration vs. Commercial Plant Economics |
84 |
4.0 |
EXPERIMENTAL |
90 |
|
4.1 |
INSTITUTE OF PAPER SCIENCE AND TECHNOLOGY BARK
DRYING VOC STUDY |
90 |
4.2 |
HIGH-TEMPERATURE HIGH-PRESSURE AIR HEATER MATERIALS
TESTING |
97 |
5.0 |
RESULTS AND DISCUSSION |
100 |
|
5.1 |
FINDINGS FOR THE DERIDDER MILL |
100 |
5.2 |
APPLICATION OF THE TECHNOLOGY TO OTHER MILLS |
102 |
6.0 |
CONCLUSIONS |
103 |
7.0 |
REFERENCES |
105 |
8.0 |
LIST OF ACRONYMS AND ABBREVIATIONS |
106 |
9.0 |
FIGURES |
108 |
|
APPENDIX A |
EQUIPMENT LIST |
131 |
APPENDIX B |
SOLAR TURBINES INCORPORATED Final Report |
136 |
|
LIST OF TABLES |
Table 3.1.2-1 |
Site Characteristics |
3 |
Table 3.1.3-1 |
Biomass Fuel Characteristics |
4 |
Table 3.1.4-1 |
Permit Levels of Recent Utility Boilers |
5 |
Table 3.2.3-1 |
Heat and Material Balance for Implementation Step 1 |
9 |
Table 3.2.3-2 |
Heat and Material Balance for Implementation Step 2 |
11 |
Table 3.2.3-3 |
Heat and Material Balance for Implementation Step 3 |
13 |
Table 3.3.1-1 |
Fuel Dryer Design Basis |
16 |
Table 3.3.1-2 |
Fuel Dryer Process Parameters |
16 |
Table 3.3.2-1 |
Fuel Specification |
18 |
Table 3.3.2-2 |
Limestone Feed Properties |
19 |
Table 3.3.2-3 |
Gasifier System Design Basis |
22 |
Table 3.3.2-4 |
Ash Properties |
23 |
Table 3.3.2-5 |
Process Air Compressor Design Parameters |
24 |
Table 3.3.2-6 |
Product Gas Composition |
25 |
Table 3.3.2-7 |
Product Gas Properties After Partial Combustion |
26 |
Table 3.3.2-8 |
Gas Turbine Air Heater Heat Exchanger AH-1 |
26 |
Table 3.3.2-9 |
Design Parameters of Emergency Spraying Nozzle |
27 |
Table 3.3.2-10 |
Product Gas Properties |
28 |
Table 3.3.2-11 |
Flare Design Parameters |
29 |
Table 3.3.2-12 |
Nitrogen Generation System Process Design Parameters |
31 |
Table 3.3.3-1 |
Boiler Performance - Original Design and 2001
Upgrade |
34 |
Table 3.3.3-2 |
Boiler #2 Heat and Mass Balance |
36 |
Table 3.3.3-3 |
Circulation Study Results |
42 |
Table 3.3.3-4 |
FD Fan and ID Fan Performance |
45 |
Table 3.3.6-1 |
HRSG Performance |
54 |
Table 3.5.1-1 |
Baseline and Modified Plant Performance Comparison |
70 |
Table 3.5.3-1 |
#2 Bark Boiler Data |
72 |
Table 3.8-1 |
Estimated Capitol Cost - Direct Cost |
81 |
Table 3.10-1 |
Input Parameters for Economic Analysis |
83 |
Table 3.10-2a |
Economic Analysis - Energy Consumption and Saving |
86 |
Table 3.10-2b |
Economic Analysis - Cost Savings and Payback Period |
87 |
Table 3.10-3a |
Economic Analysis - Alternative - Energy Consumption
and Saving |
88 |
Table 3.10-3b |
Economic Analysis - Alternative - Cost Savings and
Payback Period |
89 |
|
LIST OF FIGURES |
Figure 3.1.1-1 |
Step 1 Process Flow Diagram |
109 |
Figure 3.1.1-2 |
Step 2 Process Flow Diagram |
110 |
Figure 3.1.1-3 |
Step 3 and Overall Plant Process Flow Diagram |
111 |
Figure 3.3.1-1 |
Biomass Dryer Process Flow Diagram |
112 |
Figure 3.3.2-1 |
Gasification Process Flwo Diagram - Step 3 |
113 |
Figure 3.3.3-1 |
Internal High Temperature High Pressure Air Heater |
114 |
Figure 3.3.3-2 |
Internal HTHP Air Heater - Selected View 1 |
115 |
Figure 3.3.3-3 |
Internal HtHP Air Heater - Selected View 2 |
116 |
Figure 3.3.3-4 |
Metal Study for Internal HTHP Air Heater - No Air
Imbalance |
117 |
Figure 3.3.3-5 |
Metal Study for Internal HTHP Air Heater - With Air
Imbalance |
118 |
Figure 3.3.4-1 |
External High Temperature High Pressure Air
Heater-Design 1 |
119 |
Figure 3.3.6-1 |
HRSG Arrangement and Performance |
120 |
Figure 3.3.7-1 |
Cooling Water System |
121 |
Figure 3.3.7-2 |
Compressed Air System |
122 |
Figure 3.3.7-3 |
Electrical Single Line Diagram |
123 |
Figure 3.3.7-4 |
Bark Conveying and Delivery System |
124 |
Figure 3.3.8-1 |
Plant Construction Schedule |
125 |
Figure 3.6-1 |
Integrated Plant Layout - Sheet 1 |
126 |
Figure 3.6-1 |
Integrated Plant Layout - Sheet 2 |
127 |
Figure 3.6-1 |
Integrated Plant Layout - Sheet 3 |
128 |
Figure 4.2-1 |
Locations of Tube Samples in No. 2 Bark Boiler at
Boise DeRidder |
129 |
Figure 4.2-2 |
Test Assemblies for Tube Testing in No. 2 Bark
Boiler DeRidder |
129 |
Figure 4.2-3 |
Typical Temperature Profile for Test Tube Coupons
with air temperature control (800 H) and skin temperature control
(353 MA) |
130 |