Return to DOE Report Table of Contents

Return to Tampa Electric Company IGCC Project Table of Contents

Polk Power Station Unit 1 IGCC - 1996 DOE Annual Technical Report

Tampa Electric Company

Part 1, Pages 1 - 38.pdf
Part 2, Pages 38 - 106.pdf

Table of Contents

Part 1

1.

Project Description

1

2.

Project Highlights

4

3.

Environment/Permitting

6

4.

5.

Status of Major Contracts

10

A.

 

Detailed Professional Engineering and Technical Services

11

B.

Hot Gas Clean-Up System Design and Start-up Support

11

C.

G.E. STAG 107F Engineered Equipment Package (Power Island)

11

D.

Turnkey Air Separation Unit

12

E.

Radiant Syngas Cooling System Engineered Equipment Package

12

F.

Convective Syngas Cooling System Engineered Equipment Package

12

G.

Turnkey Sulfuric Acid Plant

13

H.

Texaco Support Services Contract (Refractory and Burners)

14

I.

Distributed Control System

14

J.

Emergency Shutdown System

15

K.

Simulator Development

16

L.

Brine Concentration Unit

16

M.

Construction Management Services

17

Process Description

19

A.

Coal Handling, Grinding, and Slurry Preparation

20

B.

Gasifier System

21

C.

Cold Gas Clean Up (CGCU) System

21

D.

Hot Gas Clean Up (HGCU) System

22

E.

Combined Cycle Power Generation

24

F.

Air Separation Unit

27

G.

Slag By-Product Handling

28

H.

Sulfuric Acid Plant

29

I.

Balance of Plant Systems

30

6.

Project Management

32

7.

Project Cost

35

8.

Part 2  

Construction Management

38

A.

Construction Plan and Project Philosophy

39

B.

Chronology of Events

42

C.

Contract Summaries

48

9.

Construction Management

70

A.

Start-Up Program

71

B.

Start-Up Activities Accomplished 1996

71

C.

Initial Operations

72

D.

Planning and Scheduling

85

E.

Chronology of Events

86

10.

Technical Papers/Conference Presentations

89

11.

Summary

91

12.

Exhibits

94

A.

Exhibit A – Project Milestone Schedule

 

B.

Exhibit B – Start-Up Schedule

 

C.

Exhibit C – Site Photographs