1. |
Introduction |
1 |
2. |
Background Information |
1 |
2.1 |
Project Organization Overview |
1 |
2.2 |
Location |
2 |
2.3 |
Process Concept |
2 |
2.4 |
Process Description |
6 |
2.5 |
Interface with Buckskin Mine Plant Expansion |
7 |
2.6 |
Major Plant Modification – PDF Deactivation Facilities |
7 |
3. |
Executive Summary for Quarters 1, 2, and 3 (October 1993 through June 1994) |
8 |
3.1 |
First Quarter Accomplishments (October through December 1993) |
8 |
3.1.1 |
3.0 Phase III – Operation, Data Collection, and Reporting |
8 |
3.2 |
Second Quarter Accomplishments (January through March 1994) |
13 |
3.2.1 |
3.0 Phase III – Operation, Data Collecting, and Reporting |
13 |
3.3 |
Third Quarter Accomplishments (April through June 1994) |
16 |
3.3.1 |
Phase III – Operation, Data Collecting, and Reporting |
16 |
4. |
Executive Summary – Fourth Quarter (July through September, 1994) |
17 |
4.1 |
Planned Scope of Work |
18 |
4.1.1 |
Accomplishments |
18 |
4.1.1.1 |
3.0 Phase III – Operation, Data Collection and Reporting |
18 |
4.1.1.1.1 |
Operation and Maintenance |
18 |
4.1.1.1.2 |
Data Collecting and Reporting |
21 |
4.1.1.1.3 |
Alternate Coal Testing |
21 |
4.1.1.1.4 |
Administration |
22 |
4.1.1.1.5 |
Equipment Modifications |
23 |
5. |
Technical Impacts on Schedule And Milestones |
24 |
6. |
Conclusions and Look Ahead |
24 |
7. |
Glossary |
26 |