Return to DOE Reports Table of Contents - S
Process Selection and
Investment Analysis, Methanation Facility for
Purox Sassi Corporation Part
1, Pages i - 106, 5.53 MB Table of Contents Introduction and Technical Summary v 1. Process Selection 1 Overview 1 Reasons for Upgrading Gas 2 Methanation Process 3 2. Basis for Design Introduction 7 Units 7 Specifications to Establish the Basis for Design 7 3. Process Description 13 Introduction 13 Benzol Wash 13 Feed Gas Compression 18 Hydrogenation 20 Sulfur and Chloride Removal 20 Stretford Plant 22 Catalytic Upgrading 26 CO2 Removal 28 Glycol Dehydration Package 34 Material Balance 35 Total Water Balance 35 A Specifications for Vessels and Tanks 107 B Direct-Fired Equipment 129 C Heat Exchangers 133 D Mechanical and Packaged Equipment 151 |