Return to DOE Report Table of Contents

EDS Coal Liquefaction Process Development: Phase V. Final Technical progress Report, Volume I - 1984

Epperly,W. R.

EXXON Research and Engineering Co.

Part 1 (1 - 103, 4.58MB)
Part 2 (104 - 203, 4.40MB)

Table of Contents

Abstract i
Introduction 1

1

Operation of Recycle Coal Liquefaction Units (RCLU) 2
 

1.1

Introduction and Summary 2

1.2

Sponsor Coal Evaluations 2
 

1.2.1

Illinois No. 6 Bituminous Coal (Monterey No. 1 Mine) 2

1.2.2

Illinois No. 6 Bituminous Coal (Burning Star No. 2. Mine) 14

1.2.3

Pittsburgh No. 8 Bituminous Coal (Ireland Mine) 14

1.2.4

Pittsburgh No. 8 Bituminous Coal (Arkwright Mine) 19

1.2.5

Wyoming Subbituminous Coal (Wydoak Mine) 22

1.2.6

Australian Black Subbituminous Coal (Wandoan Mine) 24

1.2.7

Texas Lignite (Big Brown Mine) 26

1.2.8

Texas Lignite (Martin Lake Mine) 28

1.3

Bottoms Recycle 30

1.4

ECLP Support Studies 33
 

1.4.1

Monterey No. 1 Mine Coal 33

1.4.2

Wyodak Mine Coal Operations 33

1.5

Liquefaction Reactor Hydrodynamics Tests 34

1.6

Liquefaction Reaction Solids Summary 36

1.7

Conclusions 38

2

Operation of the One Ton-Per-Day Coal Liquefaction Pilot Plant (CLPP) 43
 

2.1

Sponsor Coal Evaluations
 

2.1.1

Monterey Coal Evaluation 46

2.1.2

Burning Star Coal Evaluation 48

2.1.3

Ireland Coal Evaluation 50

2.1.4

Wyodak Coal Evaluation 54

2.1.5

Wandoan Coal Evaluation 56

2.1.6

Big Brown Lignite Evaluation 59

2.1.7

Martin Lake Lignite Evaluation 59

2.2

Evaluation of Bottoms Recycle 61

2.3

VGO Recycle Conversion Evaluation 65

2.4

Liquefaction Reactor Hydrodynamic Tests 68

2.5

Liquefaction Heat Release Studies 68

2.6

Liquefaction Reactor Solids Summary 70

2.7

Conclusions 72

3

Solvent Hydrogenation Studies 73
 

3.1

Experimental Facilities and Procedures 73

3.2

Catalyst Activity Maintenance Studies 73

3.3

ECLP Support Studies 77
 

3.3.1

Catalyst Screening (Ni/Mo-10 vs Co/Mo-20) 78

3.3.2

Heavy Solvent Process Variable Studies 78

3.3.3

Low Pressure Studies 78

3.3.4

Martin Lake Process Variable Study 83

3.3.5

ECLP Catalyst Activity Studies 83

4

Bench Units, Modeling and Correlation Studies 88
 

4.1

Tubing Bomb Autoclave Studies 88
 

4.1.1

Correlations of Coal Conversion with Coal Properties 88

4.1.2

Liquefaction Conversion of Wyoming Coal Bottoms from CLPP 91

4.1.3

Tubing Bomb Investigation of Bottoms Recycle of Sponsor Coals 91

4.1.4

Tubing Bomb Simulation of Heavy Liquid Recycle 92

4.1.5

Solvent Cracking Study in Tubing Bombs 93

4.1.6

Coal Screening and Process Variable Studies 93

4.1.7

Tubing Bomb Evaluation of Solvent Quality Effects on Bottoms Recycle Coal Conversion 94

4.1.8

Reactor Hydrodynamics Support Study 94

4.1.9

Gas Swept Mill Coal Drying Study 95

4.1.10

Slurry Drying Study 97

4.2

Design and Operation of 15 Pound-Per-Day Once Through Coal Liquefaction Unites (OTCLU) 97
 

4.2.1

Operability Study with Wyoming Coal 99

4.2.2

High Pressure, Coal-Only Study 99

4.2.3

Solvent Cracking Study on the Once-Through Coal Liquefaction Unit (OTCLU) 99

4.2.4

Liquefaction of Neat Bottoms 100

4.2.5

Vacuum Gas Oil (VGO) Conversion Study 100

4.3

EDS Coal Liquefaction Model Development 101
 

4.3.1

Empirical Coal Liquefaction Model 101

4.3.2

Fundamental Coal Liquefaction Model 103

4.3.3

Semi-Empirial Coal Liquefaction Model 104

4.3.4

Solvent Hydrogenation Model 105

4.3.5

Integrated EDS Coal Liquefaction Yield Model 105

4.3.6

EDS Generic Coal Liquefaction Model 106

5

Product Quality Studies 107
 

5.1

Summary of Research Results 107

5.2

End-Use Applications of EDS Products 108

5.3

Future Product Quality Needs 111

Laboratory Process Research and Development Bottoms Process Research

6

Coking and Gasification Studies 114
 

6.1

EDS Flexicoking Studies 114
 

6.1.1

Experimental Facilities and Procedures 114

6.1.2

Major Conclusions and Results 116

6.2

Refractory - Coal Ash Interactions Study 120

6.3

Laboratory Studies of ECLP Preheater Coking 126
 

6.3.1

Bench Slurry Coking Studies 126

6.3.2

Slurry Preheater Coking Studies on a Flow Unit 126

6.4

EDS Bottoms Characterization 136
 

6.4.1

Introduction 136

6.4.2

Major Considerations 136

ECLP Project Management, Detailed Engineering, Procurement, Construction and Operations

1

Project Management 142

2

Engineering and Procurement 142

3

Construction 142

4

Preparation and Operations 142

5

Operations 142
 

5.1

ECLP Simplified Flow Plan 142

5.2

Summary of ECLP Operations 144
 

5.2.1

ECLP Start-up and Shakedown 144

5.2.2

First Turnaround - October, 1980 144
5.2.3 Illinois Coal Testing Operation 146
5.2.4 Second ECLP Turnaround - June 1981 146
5.2.5 First Wyoming Coal Operation 147
5.2.6 Third ECLP Turnaround - November, 1981 148
5.2.7 Illinois Coal Bottoms Recycle Operation 148
5.2.8 Second Wyoming Coal Bottoms Recycle Operation 149
5.2.9 Fourth ECLP Turnaround 150
5.2.10 Texas Lignite Bottoms Recycle Operations 151
5.2.11 Final ECLP Inspection 151

5.3

ECLP Equipment Performance

152
  5.3.1 Drums 152
5.3.2 Towers 153
5.3.3 Slurry Pumps 154
5.3.4 Reactors 155
5.3.5 Valves 155
5.3.6 Miscellaneous Equipment 156

5.4

ECLP Safety and Occupational Health Programs 158

5.5

ECLP Operating Data 158

5.6

ECLP Product Shipments 161

6.0

ECLP Environmental Assessment 160

ECLP Termination of Operation

1.0

Dismantling 160

Appendices

Appendix A

ECLP Flow Plan

166

Appendix B

ECLP Operating History

168

Appendix C

ECLP Tabulated Yield Period Data

176
List of Abbreviations 184