1.0 |
Engineering Status |
2 |
1.1 |
General |
2 |
1.2 |
Civil/Structural |
2 |
1.3 |
Mechanical/Process Design |
3 |
1.4 |
Electrical Design |
6 |
1.5 |
Instrumentation and Controls |
6 |
1.6 |
Piping/Mechanical Design |
7 |
2.0 |
Technical Areas of Concern |
9 |
2.1 |
Agglomeration in Combustor and Dash Pots |
9 |
2.2 |
Nuclear Detectors |
9 |
2.3 |
Interruptible versus Firm Gas Supply |
9 |
2.4 |
Char Characteristics |
9 |
2.4.1 |
Char Characteristics |
9 |
2.4.2 |
Cyclone Performance |
10 |
2.5 |
Particulate Emissions/NOx Emissions Due to Fuel Bound Nitrogen |
11 |
2.6 |
Solids Circulation System |
11 |
2.7 |
Valve Design and Sealing Problems |
12 |
2.8 |
Deflagration Venting |
13 |
2.9 |
Combustion and Gasifier Blower Surge Control |
13 |
2.10 |
Purging of Gasifier Piping |
14 |
2.11 |
Char Burnout |
15 |
2.12 |
Repair of Refractory |
15 |
2.13 |
On-Line Capabilities |
15 |
2.14 |
Retractable Burner |
15 |
2.15 |
Air and Product Gas Mixture |
15 |
3.0 |
Attachments – Drawing and Specification Register |
16-29 |