TITLE: Tri-State Synfuels Project Review: Volume 12. Fluor Project Status.

INST.  AUTHOR: Tri-State Synfuels Co., Houston, TX.

SPONSOR: Department of Energy, Washington, DC.

LANGUAGE: English

PUB.  TYPE: Technical Report

PUB.  COUNTRY: United States

SOURCE: Department of Energy [DE],  Jun 82,  427p.

ABSTRACT:

The purpose of this report is to document and summarize activities associated with Fluor's efforts on the Tri-State Synfuels Project. The proposed facility was to be coal-to-transport fuels facility located in Henderson, Kentucky. Tri-State Synfuels Company was participating in the project as a partner of the US Department of Energy per terms of a Cooperative Agreement resulting from DOE's synfuel's program solicitation.  Fluor's initial work plan called for preliminary engineering and procurement services to the point of commitment for construction for a Sasol Fischer-Tropsch plant. Work proceeded as planned until October 1981 when results of alternative coal-to-methanol studies revealed the economic disadvantage of the Synthol design for US markets. A number of alternative process studies followed to determine the best process configuration. In January 1982 Tri-State officially announced a change from Synthol to a Methanol to Gasoline (MTG) design basis. Further evaluation and cost estimates for the MTG facility eventually led to the conclusion that, given the depressed economic outlook for alternative fuels development, the project should be terminated. Official announcement of cancellation was made on April 13, 1982. At the time of project cancellation, Fluor had completed significant portions of the preliminary engineering effort.  Included in this report are descriptions and summaries of Fluor's work during this project. In addition location of key project data and materials is identified and status reports for each operation are presented. (ERA citation 08:019511)

REPORT  NUMBER: DOE/OR/20807-T1-V.12

CONTRACT  NUMBER: FC05-81OR20807