Return to DOE Reports Table of Contents - S

Preliminary Design and Assessment of a 50,000 BPD Coal-to-Gasoline-to-Methanol Plant.

Process Engineering and Mechanical Design Reports. 
Preliminary Design and Assessment of a 50,000 BPD
Coal-to-Gasoline-to-Methanol Plant.  Volume II of V -
Deliverable 14 - August 1982. 

Stewart, R. M.
W. R. Grace & CO.

 The Ralph M. Parsons Company

Table of Contents

 

Volume II Facilities Design (Process)

 Part 1, Pages 1 - 121, 5.64 MB

1

Facilities Design

II-1-1

 

1.1

General Constraints

II-1-1

1.1.1

Codes and Standards

II-1-1

1.1.2

Regulatory Standards and Requirements

II-1-2

1.1.3

Spering Criteria

II-1-4

1.1.4

Special Metallurgical Requirements

II-1-5

1.2

Process Units Design

II-1.2.1

1.2.1

Coal Receiving and Unloading Unit 11

II-1.2.1-1

1.2.2

Coal Conveying and Storage Unit 12

II-1.2.2-1

1.2.3

Coal Stacking and Reclaiming Unit 13

II-1-2.3-1

1.2.4

Solid Waste Collection and Disposal Unit 14

II-1.2.4-1

Part 2, Pages 122 - 236, 4.41 MB

 

1.2.5

Gasification Unit 21

II-1.2.5-1

1.2.6

Oxygen Unit 22

II-1.2.6-1

1.2.7

CO Shift Unit 23

II-1.2.7-1

1.2.8

Coal Grinding and Slurry Preparation Unit 24

II-1.2.8-1

1.2.9

Methanol Synthesis Unit 25

II-1.2.9-1

Part 3, Pages 237 - 328, 4.49 MB

 

1.2.10

Ammonia Recovery Unit 26

II-1.2.10-1

1.2.11

Effluent Water Treatment (Texaco) Unit 27

II-1.2.11-1

1.2.12

Methanol-to-Gasoline Unit 31

II-1.2.12-1

1.2.13

Gas Fractionation Unit 32

II-1.2.13-1

Part 4,, Pages 329 - 468, 5.25 MB

 

1.2.14

HF Alkylation Unit 33

II-1.2.14-1

1.2.15

Acid Gas Removal Unit 34

II-1.2.15-1

1.2.16

Sulfur Recovery (Claus) Unit 36

II-1.2.16-1

1.2.17

Sulfur Removal (BSRP) Unit 37

II-1.2.17-1

1.2.18

Heavy Gasoline Treating Unit 38

II-1.2.18-1

1.2.19

Process Water Treatment Unit 39

II-1.2.19-1